Pechea Wind Project
Location: Pechea, Galati County | Year: 2023
Project Overview: Pechea project is a wind farm located in Romania, Galati County, including 2 V162 6.2 MW onshore wind turbines with an installed capacity of 12.4 MW.
Our Scope:
- Electrical measurements – High Voltage measurements including transformer measurements + acceptance measurements of sockets and lighting
- Low voltage inspection - earthing resistance measurement and step/touch voltage of WTG earthing system
- Insulation/main circuit resistance tests for SWG
- Routing/Connection of High Voltage cable on Transformer
- Phase correspondence and conductor resistance measurements for HV cable
- Routing/Connection of High Voltage cable on Transformer
- Routing/Connecting of High Voltage cable on Switchgear
- Electrical Works Manager - Performing the function of the manager of electrical works including the entries to the construction log, coordination of the turbines' energization
Status: Completed